Project Data
-
RegionCentral Queensland
-
LocationCentral Highlands Region
-
ClientTraffic and Main Roads
-
Duration / Date2014
-
Categories
Project Scope
TEG Consulting Engineers was engaged as Project Manager to manage the administration of the 2014 14D NDRRA Recovery works for TMR in the Central Highlands Region. The project involved undertaking emergent works to repair TMR’s damaged road network in the Fitzroy Region.
This role required the following:
- Scoping sites, preparing estimates and taking photographic evidence.
- Engaging Council to undertake the works as per the scoping inspection.
- Prepare and report on financial and construction activities to the principal.
- Assessing Contractors progress claims.
- Maintaining registers.
- Preparing emergent works submission documents for Queensland Reconstruction Authority Approval.
- Regularly liaise with all stakeholders.
Our Involvement
TEG Consulting as the Project Manager, managed the 14D flooding event for TMR engaging Central Highlands Regional Council under a sole invitee to complete the recovery works. The work comprised of gravel re-sheeting works on the Tambo Springsure Road valued at 150 thousand. The management of the works included processing claims, undertaking inspections, taking photographs for records and completing the final submission to the QRA.
Project Outcomes
All emergent works and submission documents were completed within the State Project Office (SPO) and Queensland Reconstruction Authority (QRA) timeframe and guidelines.
Key Personnel
-
Consulting Engineers:Sean Edwards
-
Client Representative:Guru Balasubramanian